Camp Pendleton Brig Renovation and New Riot Gear Storage Building

Military | Design-Build

The brig, a 2-story, 65,271 SF pre-trial holding/detention facility, was updated throughout. The roofing, electrical, lighting, HVAC, security, fire alarm, telecom and public address systems were included in the upgrades, as well as minor structural and landscape improvements. The new, 1-story riot gear storage building was constructed out of CMU block and metal roofing.

Structural EngineerBWE
Civil EngineerBWE
Land SurveyorBWE
OwnerUS Navy
ArchitectKMA Architecture & Engineering
Completion Date2012
Construction Cost$5.6 Million